www.sskhepl.com

Projects

LUNI II HEP



Luni-II HEP is allotted by the Government of Himachal Pradesh to M/s Sri Sai Krishna Hydro Energies Private Limited on Build, Own, Operate and Maintain (BOOM)Basic vide Memorandum Of Understanding Signed on dated 29th, November,2004.
The site of Luni-II HEP can be approached through Baijnath-Karnathu road. Karnathu village is at a distance of 10KM from Baijnath Town. From Karnathu village the length of project is 6.5KM upto Luni-II Power House
Luni-II HEP is upstream project of the proposed diversion site of the scheme allotted to M/s Subhash Project Limited the developer of Luni-I HEP.
For the construction of Luni-II HEP, 2.62Hac of forest land is required and the same was diverted by Ministry of Environment and Forest vide their Letter No. 9-HPB632/2005-CHA/36 on dated 22nd,December, 2005 unedr Forest Conservation Act, 1980. Construction activity in Luni-II HEP commenced on 14th April, 2006 and started the generation in 12th, November,2009.
Luni-II HEP is a run-of-the river type scheme on Luni Khad, a tributary of river Binua Khad. The scheme envisages diversion of inflow of Luni Khad by constructing a trench weir. The diverted inflow will be carried through conveyance channel to a surface disilting tank, which will be designed to exclude all silt particles down to 0.20MM size. The slit free water will be carried through water conductor system (2200mtr long) upto forebay. The inflow from forebay will be lead to surface power house through a 900mtr long surface penstock to feed two number Pelton Turbine driven generation of 2.50MW each. The outflow from Turbine is led through a Tail Race pipe (60mtr Long) to upstream of intake of M/s Subhash Project the developer of Luni-I HEP.
A switch yard is proposed along the side of power house building. The power generated from this project will be fed into HPSEB 132KV Substation at Dehan.



LUNI III HEP



Luni-III HEP is allotted by the Government of Himachal Pradesh to M/s Sri Sai Krishna Hydro Energies Private Limited on Build, Own, Operate and Maintain (BOOM)Basic vide Memorandum Of Understanding Signed on dated 29th, November,2004.
The site of Luni-III HEP can be approached through Baijnath-Karnathu road. Karnathu village is at a distance of 10KM from Baijnath Town. From Karnathu village the length of project is 10KM upto Luni-III Power House
Luni-III HEP is upstream project of the proposed diversion site of the scheme allotted to M/s Sri Sai Krishna Hydro Energies Private Limited the developer of Luni-II HEP.
For the construction of Luni-III HEP, 4.63Hac of forest land is required and the same was diverted by Ministry of Environment and Forest vide their Letter No. 9-HPB634/2005-CHA/39 on dated 22nd,December, 2005 under Forest Conservation Act, 1980. Construction activity in Luni-II HEP commenced on 1st April, 2006 and started the generation in 31st, May,2009.
Luni-III HEP is a run-of-the river type scheme on Luni Khad, a tributary of river Binua Khad. The scheme envisages diversion of inflow of Luni Khad by constructing a trench weir. The diverted inflow will be carried through conveyance Tunnel (150mtr long) to a Underground disilting tank, which will be designed to exclude all silt particles down to 0.20MM size. The slit free water will be carried through water conductor system (600mtr long) upto forebay. The inflow from forebay will be lead to surface power house through a 1250mtr long surface penstock to feed two number Pelton Turbine driven generation of 2.50MW each. The outflow from Turbine is led through a Tail Race pipe (30mtr Long) to upstream of intake of M/s Sri Sai Krishna Hydro Energies Private Limited the developer of Luni-II HEP.
A switch yard is proposed along the side of power house building. The power generated from this project will be fed into HPSEB 132KV Substation at Dehan.